A24 Robin Hood junction improvement

Details of the design and construction of the A24 Robin Hood junction improvements.

(Position at July 2021)

Background

West of Horsham, south of Broadbridge Heath village, has seen a large expansion of housing since 2010.

Part of the planning approval of the housing included the developer providing funding for changes to the roundabout at A24 Robin Hood junction. This formed part of a formal planning agreement.

The junction is impacted by traffic congestion in the morning and evening peak hours. This will continue to increase as the development areas are built, and with the general increase in background traffic. West Sussex County Council (WSCC) appreciates that currently, with the COVID-19 restrictions, traffic flows have been artificially suppressed, but in the longer term they will increase again.

Proposed scheme

WSCC is responsible for the design and delivery of the junction improvement, which consists of:

  • widening of the A24 in the southbound direction from two lanes to four lanes
  • widening of the A24 in the northbound direction from two lanes to three lanes
  • widening of the exit from Warnham Road on to the roundabout
  • traffic signal control on the A24 approaches and on the Warnham Road, with traffic signal control on the roundabout
  • provision of a signalised 'Toucan' crossing across the Northbound exit of the A24 (towards A24 Great Daux)
  • improved footway and cycleway connection Warnham Road to Robin Hood Lane and the Public Right of Way.

Benefits

The scheme will provide benefits through:

  • providing increased road capacity at the junction to allow for increased traffic due to local developments and through traffic
  • the provision of traffic lights with sensors, which adjust signal timings according to queuing levels to help ease congestion, on signalled approaches (not Robin Hood Lane) will help manage flows in the peak and off-peak periods
  • new crossing facilities for pedestrians and cyclists linking Warnham Park and the Public Right of Way with Warnham Road via new Toucan crossings.

Public engagement

This was completed as part of the developer's planning application/permission during 2009 and 2010.

This web page will be updated as milestones are reached and then, once construction works begin, weekly or fortnightly, depending on work progress. Advance notices of the start of works will be displayed around the junction and traffic management restrictions will also be published.

Local residents and businesses will be able to sign up to a weekly email update from the contractor, by providing their email address, and regular updates will be posted on this page. Please use the Landbuild address robinhoodroundabout@landbuild.co.uk to express your interest.

Find more information about the Land North of Horsham development, or contact the Community Liaison Team directly by emailing community@landnorthofhorsham.co.uk. We are aware of their works on the A264 for vegetation clearance and Rusper Road south for a new traffic island and pedestrian crossing point.

Southern Water and Clancy Ltd are also currently undertaking works at A24 Robin Hood and along the Daux Path for a new sewer. For further information, contact Steve Anthony, Customer Service Manager, at Clancy Docwra by phoning 07926 535414 or emailing steve.anthony@theclancygroup.co.uk.

Clancy have completed their drilling under the A24 Robin Hood roundabout and are now working, under traffic lights, along Warnham Road and drilling under Robin Hood Lane towards Daux Hill.

Programme

Landbuild Ltd completed their works as programmed at the end of November 2020 for the advanced vegetation clearance and drainage investigations/remedials at the junction. Utility investigations have also been completed.

An additional landscape and plants plan have been added (see below), which indicates the landscape mitigation that will be included in the scheme. Bat boxes were also provided as part of the advanced works to replace potential roosts lost due to the clearance works.

WSCC Major Projects team is in liaison with our colleagues in Highways Development Control and Streetworks, along with the Legal and General team working on the A264 and Rusper Road, to examine the co-ordination of construction, traffic management and any necessary closures and diversion works. These meetings have now taken place and regular update meetings have been agreed.

Weekly update

29 July 2021

Thank you for your continued patience during the works. Traffic is now operating under narrow lanes for Phase 2.

Advanced note: We will be carrying out the full resurfacing of the scheme under night-time closures from 14 to 17 August 2021 (plus 18 August if required). This closure is being combined with the resurfacing of the Great Daux Roundabout and A24 south bound main carriageway to minimise disruption to the network.

Works completed this week

  • Warnham Road island kerbing completed.
  • Southern central island kerbing.
  • Signal poles being installed throughout.
  • Northern central island kerbing.

Works to take place next week (2-6 August)

  • Kerbing to northern central island including setting traffic signal ducts and pits.
  • Kerbing to southern central island including setting traffic signal ducts and pits.
  • Traffic signal equipment installation and cabling to continue.

Supporting documents

 
Last updated:
29 July 2021
Share this
Share this

Do you have any feedback about this page?

Help us improve this website

Let us know if this page was helpful so we can make improvements. Add a star rating and leave your feedback below to show how useful you found this page.

Rate this page:
Clear star rating...
  • West Sussex County Council will only use this email address to respond to any issues raised.