A2011 Crawley Avenue - Hazelwick junction

West Sussex County Council is developing the A2011 Crawley Avenue and Hazelwick junction improvement scheme.

1 Scheme overview

The West Sussex Transport Plan 2022 to 2036 identifies this junction, including active travel and public transport improvements, as a priority for investment between 2022 and 2027. The scheme also supports the aims of the Crawley Local Cycling and Walking Infrastructure Plan (LCWIP).

The LCWIP highlights how busy roads and dual carriageways in Crawley can make it difficult for people to walk and cycle between communities. Air quality is also a concern in this area, with an Air Quality Management Area (AQMA) around Hazelwick roundabout.

The county council approved the scheme for inclusion in its capital programme in February 2026.

The scheme will transform Hazelwick roundabout into a fully signalised junction. It forms part of the mitigation measures for the Forge Wood development.

The proposed improvements include:

  • new traffic signals around the roundabout
  • improved road markings and signage
  • new and upgraded walking and cycling facilities
  • signal-controlled crossings for pedestrians and cyclists
  • a new bus lane
  • carriageway widening within the existing highway boundary
  • low-noise road surfacing
  • reduced speed limits on sections of the A2011 Crawley Avenue and Hazelwick roundabout

The scheme aims to:

  • reduce congestion
  • improve road safety and reduce collision-related casualties
  • improve journey time reliability for all types of transport
  • improve walking and cycling connections
  • increase travel choice and support sustainable transport
  • minimise impacts on the natural, built and historic environment
  • improve bus journey reliability through dedicated bus lanes and priority measures
  • minimise carbon emissions, air quality impacts and visual impacts from transport infrastructure

2 Latest update

The A2011 Crawley Avenue and Hazelwick junction improvement project is in the preliminary design stage. We expect to complete this stage by January 2028, followed by a review that will finish by March 2028.

In recent months, we have:

  • reviewed the feasibility designs
  • refined the concept design
  • collected traffic data
  • validated traffic modelling
  • planned surveys for the next stage of design which is due to start in January 2027

This work helps us assess possible improvement options and identify solutions to issues we found during the feasibility stage.

We use the findings to improve the preliminary design, basing proposals on evidence and accounting for local transport and environmental factors.

3 Public consultation

You can see the:

  • 2025 public consultation summary results
  • Hazelwick junction consultation results
  • Hazelwick junction technical drawings

Find them on the A2011 Crawley Avenue - Hazelwick and Tushmore junction improvements consultation web page.

4 Timelines

The proposed timelines for the scheme are:

  • preliminary design by March 2028
  • detailed design by September 2029

We do not have a proposed date for the start of construction yet.

We will update these dates when we have more information.

Last updated:
23 November 2026
Share this
Share this

Help us improve this website

Let us know if this page was helpful so we can make improvements. Leave your feedback below to show how useful you found this page.

  • West Sussex County Council will only use this email address to respond to any issues raised.