County Council continues to pursue resolution to ongoing situation on A29, Pulborough

 

Release date: 18 December 2025

West Sussex County Council remains committed to resolving the ongoing situation with the A29, Church Hill in Pulborough following a landslide in late December 2022. We will continue to work towards reaching a resolution which will be to the benefit of residents, businesses and visitors across Pulborough.

The landslide occurred on the steep embankments situated at the narrowest part of the A29. These embankments are in private ownership and the council does not have legal rights to enter or carry out work required on this private land without the permission of the owners.

Shortly after the landslide, geo-technical experts assessed the embankments and advised that due to the established instability of the land on both sides, it is not safe to fully reopen the road to vehicles and pedestrians. We continue to regularly monitor the site to ensure it remains safe for the current use arrangements.

Since the initial incident we have engaged in regular discussions with the landowners, however, when we were not able to reach an agreement with them as quickly as we had hoped, we installed traffic lights and concrete blocks to allow safe single-file traffic in April 2023.

The private ownership of the embankments is still the main challenge the council faces when attempting to achieve a long-term solution. Legal options to address the lack of an agreed solution are limited and the statutory notices served on the landowners to allow work on the embankments have been appealed  by them and referred to the magistrates’ court system which is suffering from lengthy delays.  

Whilst we have not made as much progress as we were hoping to have done this year, there is a prospect of some being made soon, with a court hearing having been set for January 2026.

If this route to have the planned works approved through the courts does not provide the much-needed solution in a timely way, the County Council will keep other legal routes under active consideration. However, we must allow the current court process to reach a conclusion before we begin an alternative route.

In the meantime, the single lane signal-controlled arrangement is regularly reviewed to ensure it continues to provide a safe and workable temporary solution.

We appreciate the ongoing delay in resolving the situation has caused frustration locally, and we will keep focussed on exploring all options to reach a resolution, including engaging with the landowners if they are open to further discussion. We will also continue to keep residents and stakeholders informed of our progress as updates are available to be provided.

 

Share this

Help us improve this website

Let us know if this page was helpful so we can make improvements. Leave your feedback below to show how useful you found this page.

  • West Sussex County Council will only use this email address to respond to any issues raised.

Last updated:
18 December 2025
Share this