Work starts next week on building Findon/Findon Valley shared cycleway and walkway

"The long-term benefits of a 2km-long cycleway/walkway route off the A24 are clear"

 

Release dated: 26 August 2022

Construction of a 2km-long shared cycleway/walkway route, connecting Findon Valley with the South Downs National Park gateway of Findon Village, is scheduled to start on Tuesday (30 August).

The new route will provide a link for those wanting to opt for a more active way of travelling to see one of the county’s stunning attractions – the South Downs. It also has the advantage of linking in with an existing cycleway south of the Findon Valley shops, towards the A27 and a signed route into Worthing town centre.

The cycleway/walkway will be paid for with money from a Government grant for Active Travel projects. It is part of the County Council’s Active Travel improvement proposals, which aim to:

  • make walking and cycling to work, education and leisure activities more attractive
  • improve health and wellbeing by offering eco-friendly travel choices
  • broaden travel choices by offering safer, quick and easy walking and cycling options, particularly for short journeys
  • support zero emission journeys and reduce reliance on car travel.

The shared cycle/footway will be built on the eastern side of the A24 from its junction with Findon High Street southwards to the May Tree Avenue junction.

A significant stretch of the route will be off-carriageway and on the eastern side of the A24, with the rest on quiet, residential roads.

The route will divert from the A24 behind the Findon Valley shops on-carriageway via May Tree Avenue and Lime Tree Avenue. The cycle route here will comprise traffic signage and cycle road markings only.

The scheme will be built in five phases, with the first starting on Tuesday – subject to unforeseen factors, such as severe weather.

Phase 1 High Street to Cross Lane.

Phase 2 Junction works at Cross Lane/A24 junction.

Phase 3 Junction works at Nepcote/A24 junction.

Phase 4 Nepcote to May Tree Avenue.

Phase 5 May Tree Avenue/ Lime Tree Avenue.

Single traffic lanes will be maintained on the dual carriageway A24 Findon Bypass for most of the project. Some tree works, carriageway surfacing, and kerbing works will require temporary traffic lights for the protection of both the public and workforce. These periods will be kept to a minimum and at off-peak times, where possible.

Construction of the shared path will require temporary closures to the eastern footpath along the A24 while works progress. However, the works will be done in phases to limit the closure lengths and the western footpath will remain open to pedestrians throughout.

A West Sussex County Council spokesperson said: “Construction projects such as this will involve some short-term disruption, for which we apologise.

“However, we will work with the contractor to try to minimise inconvenience as much as possible and the long-term benefits of a 2km-long cycleway/walkway route off the A24 are clear and it was identified as a priority in the West Sussex Walking and Cycling Strategy 2016-2026.”

The project is scheduled to finish in mid-January 2023.

Share this

Do you have any feedback about this page?

Help us improve this website

Let us know if this page was helpful so we can make improvements. Add a star rating and leave your feedback below to show how useful you found this page.

Rate this page:
Clear star rating...
  • West Sussex County Council will only use this email address to respond to any issues raised.

Share this